UK & Ireland2023Illustrative reference

Two server rooms migrated in one weekend, London

A consolidated move of two legacy server rooms into a colocation suite over a single 54-hour window, with rollback positions agreed before anything was de-racked.

duration
54-hour window, 7 weeks preparation
duration
engineers on site
11
engineers on site
country
GB
country
measured outcomes
4
measured outcomes

38

racks migrated

54h

business window

412

drives sanitised & certified

20h

inside the deadline

The challenge

Two server rooms, 38 racks of mixed-age hardware, undocumented cabling and a business that could not be offline past Monday 06:00. Legacy equipment had no current spares, and two applications had no tested failover. The client's instinct was a big-bang move; the risk profile said otherwise.

The result

The migration completed at 03:40 on Sunday, twenty hours inside the window. Two applications were reverted to the rollback position when post-move validation failed, then migrated successfully in the second batch — the plan absorbed the failure instead of the business absorbing it. All 412 drives sanitised with per-drive certificates.

“The rollback positions are why we signed. Nobody else put in writing how they would undo it.”
Financial services firm — placeholder

Scope delivered

  • Full pre-move inventory and serial reconciliation of 38 racks
  • Staged migration plan with three batches and defined rollback positions
  • New racks, structured cabling and network bring-up at the destination
  • Out-of-hours de-rack, transport with shock monitoring, and re-installation
  • Post-move certification and acceptance testing before business hours
  • Decommissioning of the vacated rooms with media sanitisation to policy