420-rack hyperscale fit-out, Frankfurt
Three data halls brought to production in a single quarter, with configuration drift controlled by wave-based validation rather than end-of-project inspection.
- duration
- 11 weeks
- duration
- engineers on site
- 14
- engineers on site
- country
- DE
- country
- measured outcomes
- 4
- measured outcomes
420
racks delivered
3,100+
servers installed
11 wks
to acceptance
0
post-handover reworks
The challenge
The client had committed to a capacity launch date with three halls still empty. Their in-house team could not scale past 40 racks a week, and the vendor hardware was arriving in overlapping shipments with inconsistent firmware levels. The real risk was not speed — it was installing 420 racks at four different firmware baselines and discovering it at acceptance.
The result
All three halls reached acceptance eleven weeks after mobilisation, on the committed date. Because firmware versions were recorded per node from the first wave, a vendor firmware defect was caught in week two on 36 units instead of at acceptance across 3,100. Zero racks required rework after handover.
“The wave gates were the difference. They found a firmware defect in week two that would have cost us the launch date in week eleven.”
Scope delivered
- Rack assembly and device mounting across three halls, 420 racks
- Cat 6A and OS2 structured cabling with 100% link certification
- Server population, firmware baseline and BIOS/BMC configuration
- Wave-based build with validation gates between waves
- Burn-in across all nodes with per-serial results
- Full acceptance testing including power-path and failover verification
Services used
Sectors: hyperscale · colocation
More delivery work
All projectsIberia · 2024
Rolling customer deployments, Lisbon colocation
A standing delivery partnership absorbing customer deployment requests the provider's in-house team could not schedule, executed to the facility's own standard and paperwork.
Read caseUK & Ireland · 2023
Two server rooms migrated in one weekend, London
A consolidated move of two legacy server rooms into a colocation suite over a single 54-hour window, with rollback positions agreed before anything was de-racked.
Read caseBenelux · 2024
14,000-link fibre and copper refresh, Amsterdam
A live-facility cabling refresh replacing end-of-life OM3 with OM4 and OS2, delivered in occupied halls without a single unplanned customer outage.
Read case