14,000-link fibre and copper refresh, Amsterdam

A live-facility cabling refresh replacing end-of-life OM3 with OM4 and OS2, delivered in occupied halls without a single unplanned customer outage.

duration
16 weeks
duration
engineers on site
9
engineers on site
country
NL
country
measured outcomes
4
measured outcomes

14,000

links installed

100%

certified, native exports

0

unplanned outages

340

re-terminations to pass

The challenge

The facility was fully occupied throughout. Cable routes were saturated, some containment was undocumented, and the operator could not accept a single unplanned outage. A conventional rip-and-replace approach would have put live customer links at risk for four months.

The result

Zero unplanned outages across 16 weeks of live-facility work. Every link certified with a native export, and 340 links that failed initial certification were re-terminated and re-tested on site. The as-built administration now matches the physical plant — the operator's first audit since the refresh closed with no cabling findings.

“They told us which links failed and re-tested them in front of us. That is not how our previous contractor worked.”
Network operator — placeholder

Scope delivered

  • Route survey and containment capacity assessment across four halls
  • New containment installation and route remediation
  • 14,000 links installed: OM4 multimode, OS2 singlemode and Cat 6A
  • Live-service migration using pre-tested parallel paths
  • 100% certification with native test exports per link
  • Administration rebuild to TIA-606-D with the operator's naming scheme