14,000-link fibre and copper refresh, Amsterdam
A live-facility cabling refresh replacing end-of-life OM3 with OM4 and OS2, delivered in occupied halls without a single unplanned customer outage.
- duration
- 16 weeks
- duration
- engineers on site
- 9
- engineers on site
- country
- NL
- country
- measured outcomes
- 4
- measured outcomes
14,000
links installed
100%
certified, native exports
0
unplanned outages
340
re-terminations to pass
The challenge
The facility was fully occupied throughout. Cable routes were saturated, some containment was undocumented, and the operator could not accept a single unplanned outage. A conventional rip-and-replace approach would have put live customer links at risk for four months.
The result
Zero unplanned outages across 16 weeks of live-facility work. Every link certified with a native export, and 340 links that failed initial certification were re-terminated and re-tested on site. The as-built administration now matches the physical plant — the operator's first audit since the refresh closed with no cabling findings.
“They told us which links failed and re-tested them in front of us. That is not how our previous contractor worked.”
Scope delivered
- Route survey and containment capacity assessment across four halls
- New containment installation and route remediation
- 14,000 links installed: OM4 multimode, OS2 singlemode and Cat 6A
- Live-service migration using pre-tested parallel paths
- 100% certification with native test exports per link
- Administration rebuild to TIA-606-D with the operator's naming scheme
Services used
Sectors: telecom · colocation
More delivery work
All projectsDACH · 2024
420-rack hyperscale fit-out, Frankfurt
Three data halls brought to production in a single quarter, with configuration drift controlled by wave-based validation rather than end-of-project inspection.
Read caseIberia · 2024
Rolling customer deployments, Lisbon colocation
A standing delivery partnership absorbing customer deployment requests the provider's in-house team could not schedule, executed to the facility's own standard and paperwork.
Read caseUK & Ireland · 2023
Two server rooms migrated in one weekend, London
A consolidated move of two legacy server rooms into a colocation suite over a single 54-hour window, with rollback positions agreed before anything was de-racked.
Read case