Remote hands SLAs: what to put in the contract

Response time is the number everyone negotiates and the one that matters least. These clauses decide whether the service actually works.

Tomasz Wójcik, Field Support Manager CEE

Published 2025-03-11

Download .md

Every remote hands contract argues about response time. Almost none argue about the clauses that determine whether the service is any good.

Response time matters, but it is the easiest number to promise and the hardest to verify. The following clauses are the ones that separate a service that helps from a service that generates tickets.

Define the task catalogue

"Remote hands" covers anything from reading an LED to replacing a motherboard. List the task types, and split them into procedural and skilled. Procedural tasks are executed as instructed. Skilled tasks require an engineer who understands the platform, and should be priced accordingly — otherwise you will be sent whoever is nearest rather than whoever is capable.

Evidence as a deliverable, not a courtesy

Specify what closure means: photographs before and after, console output where relevant, timestamps, and the reference number on every item. This clause alone changes the character of the service, because it makes the work auditable without you being present.

Access and induction lead times

If your site requires 24 hours' notice for access, a two-hour response commitment is fiction. State your induction and access process in the contract, and make the SLA clock start from confirmed access rather than from ticket creation. Both sides benefit from an honest clock.

Change control boundaries

State explicitly what the provider may not do: no configuration changes without a change record, no production reboots without approval, no undocumented cable moves. A provider that treats this as optional will eventually make a change you did not authorise, at a time you did not choose.

Spares and chain of custody

If the provider holds spares, specify the stock list, replenishment thresholds, and the movement log. If they handle media or assets, specify chain-of-custody records and sanitisation methods. Missing spares turn a two-hour fix into a two-day outage.

Escalation with names

Not "escalate to the account manager" but a named path with timeframes: engineer to duty lead at 30 minutes, to account lead at two hours, to delivery director at four. When something goes wrong at 02:00, an escalation path with names is worth more than an SLA percentage.

Reporting that you can act on

Monthly reporting should include SLA performance, task mix, recurring faults and recommendations. The recurring-fault section is the valuable one: it is how a provider demonstrates they are removing work rather than billing it.

Exit

State what you receive on termination: task history, spares reconciliation, documentation of any changes made on your estate, and the return of anything held on your behalf. Nobody negotiates the exit clause while the relationship is good, and everybody needs it later.

The shortest useful test of a remote hands contract: *what document will we receive after a task, and who will call us if it cannot be completed as instructed?* If both answers are specific, the contract is probably sound.
remote-handsSLAcontracts